Title
Subject: Swinerton Builders - Police Administration Building
From: Public Works Agency
Recommendation: Adopt a Resolution authorizing the City Administrator to amend the professional services contract with Swinerton Builders for Construction Manager At-Risk Services to include the construction phase of the Police Administration Building Weak Story Seismic Retrofit Phase I Project and to either (1) increase the contract compensation amount by $8 million for a total contract amount not to exceed $8.5 million if the Federal government approves Federal Emergency Management Agency ("FEMA") Grant Funds for the project or, (2) increase the contract compensation amount by $5.5 million of Measure I funding (Bond funding for public safety purposes) for a total contract amount of $6 million, if FEMA grant funds are not approved (PURSUANT TO SECTION 902-E OF THE CITY CHARTER, THIS ITEM REQUIRES A 2/3 VOTE OF THE COUNCIL - 6 AFFIRMATIVE VOTES)
Body
[Enter body here.]